6 Calculation and installation of lining brick used in ball mill
www.aluminaball.net 11/27/2007 4:46:36 PM




Before installation, all the partial remaining of bricks and cement on the inner surface should be thovoughly removed, The smooth surface should be made hoarse, damaged iron surface should be reparied through welding if it is badly worn.
For installation,grout width should be about 1mm using #425 white cement, Brick should be laid from level area of ball mill and moving upward.
Surface area should be clean and kept wet by spraying water for 1 to 2 days to increase the cohesion for max hardness.
Finally,the ball mill should be filled with water for minimum of 10 days.


     

 

 


 Adopting combination            totally adopting ladder type brick              worng installation 
of ladder type brick and 
         column brick 

 

Add: DongJian Building 12 F, FenJiang Load, Chancheng Distric,Foshan City   MSN Online
P.C.: 528000 TEL:86-757-82261108  Fax:86-757-82263811  E-mail:fswangao@sina.com
Designed by Global Vision Group (HK) Co.Ltd
Pls view the web under resolution of 1024*768 Compatible Web:IE6.0